C-65.1, r. 8.01 - Pilot project to facilitate payment to enterprises that are parties to public construction work contracts and related public subcontracts

Full text
15. The general contractor must pay the amount owing to its subcontractor on or before the 5th day of the month following the month for which the general contractor submitted or should have submitted a payment application to the public body.
M.O. 2018-01, s. 15.
In force: 2018-08-02
15. The general contractor must pay the amount owing to its subcontractor on or before the 5th day of the month following the month for which the general contractor submitted or should have submitted a payment application to the public body.
M.O. 2018-01, s. 15.